Speed Refinery Unit, Skouteras Municipality
Maximum capacity 1,000 m3/day
Argini Wastewater Treatment Plant
Project description
In the fall of 2024, following a public tender by the Agrinio Water Resources and Sewage Authority, our company YPAEN IKE proceeded with the supply and installation of a filtration system in Skoutera, Municipality of Agrinio, with a capacity of 42 m3/h, i.e. a total of 1,008 m3 on a daily basis.
Within the framework of the implementation of the relevant contract, YPAEN IKE undertook the supply and installation of all the necessary electromechanical equipment of the filtration system (filters, pumps, tanks, shelter, fencing, etc.), made the necessary hydraulic connections, and carried out all the necessary electrical work.
Finally, it undertook the adjustment and parameterization of the individual elements of the filtration system (chemical dosage, etc.), so that they would optimally meet the required capacity.
Image Gallery